Discovery tells you what is worth doing; scoping decides exactly what you will do, by when, with whose help, and how everyone will know it worked. A good scope is the difference between a pilot that ends in a confident yes or no and one that drifts for months. This lesson covers choosing between a proof of concept, a pilot and a production project, writing success criteria that cannot be argued about later, drawing scope boundaries, listing the customer's own commitments, building a timeline with go/no-go gates, keeping a risk register, and handling change without losing control.
- Choose between a proof of concept, a pilot and a production engagement
- Write measurable success criteria and explicit in-scope and out-of-scope lists
- Record assumptions and customer dependencies with owners and dates
- Build a timeboxed plan with milestones and go/no-go gates
- Maintain a risk register and a lightweight change-control process
Proof of concept, pilot or production?
| Type | Question it answers | Typical length | Real users and data? |
|---|---|---|---|
| Proof of concept (POC) | Can this work at all technically? | 1-3 weeks | Sample data, no real users |
| Pilot | Does it deliver value in their real workflow? | 4-12 weeks | Real data, a limited group of real users |
| Production rollout | Can it run for everyone, reliably and supported? | Months | Everyone, with SLAs |
Match the engagement to the open question. If feasibility is genuinely uncertain (can we extract fields from these scanned forms at all?), run a short POC first. If feasibility is clear and the doubt is about value and adoption, go straight to a pilot with real users, because a POC on sample data proves nothing about the workflow. Many stalled AI projects are endless POCs: technically impressive, never touching a real user.
Success criteria and scope boundaries
Turn the discovery metric into criteria that are specific, measurable, owned and time-bound, and write down what you are explicitly not doing. An out-of-scope list is as important as the in-scope one: it is what you point to when someone asks for one more feature in week four.
pilot: motor-claims-clause-assistant
duration_weeks: 6
users: 12 claims handlers in the Leeds team
success_criteria:
primary: median handling time for pilot users down >= 30% vs 2-week baseline
guardrails:
- clause-lookup accuracy >= 95% on a 200-case expert-reviewed set
- no increase in escalation rate
- weekly active use >= 80% of pilot users by week 5
in_scope:
- motor policies, English-language PDFs
- read-only access to the claims view
- web app behind company SSO
out_of_scope:
- home and commercial policies
- writing back to the claims system
- mobile app
decision: go/no-go for wider rollout at end of week 6, sponsor decidesAgree what happens on a 'no' as well as a 'yes'. If the pilot misses its criteria, a clear stop with lessons learned is a good outcome; a vague extension is not.
Assumptions and customer dependencies
Most pilot delays are caused by things the customer must provide, not by engineering. List every dependency with an owner and a date, and treat late dependencies as schedule changes, visibly.
| Dependency | Owner | Needed by | If late |
|---|---|---|---|
| Read-only access to claims view | Claims IT lead | End of week 1 | Build slips one week per week late |
| Policy PDF export | Document management team | End of week 1 | Use 500-document sample; accuracy risk |
| 2 hours/week of expert reviewer time | Claims team lead | Weeks 2-6 | Evaluation set incomplete |
| Security review slot | InfoSec | Week 3 | No production data in app until approved |
| SSO app registration | Identity team | Week 4 | Pilot users cannot log in |
Also write down assumptions: things you believe but have not verified, such as "PDFs contain selectable text, not scanned images" or "the claims view refreshes nightly". Verify the riskiest ones in the first week; a wrong assumption found in week five is a crisis, found in week one it is a plan change.
A timeline with gates
- Week 0: kickoff. Confirm scope, success criteria, dependencies, communication rhythm and decision makers.
- Week 1: foundations. Access, data samples, baseline measurement, riskiest assumptions tested.
- Weeks 2-3: first working version with real data, shown to users; evaluation set built with experts.
- Gate (end of week 3): is it on track to meet criteria? Adjust, continue or stop.
- Weeks 4-5: users on it daily, weekly iterations, security approval, monitoring in place.
- Week 6: measure and decide. Compare against baseline, present evidence, sponsor decides go or no-go.
Estimate in ranges and say what drives the uncertainty ("2-4 weeks, depending on whether the forms are scanned"). When you cannot estimate at all, schedule a short spike, a timeboxed investigation whose only output is the information needed to estimate.
Risks and change control
Keep a short risk register from day one: each risk with likelihood, impact, mitigation and owner, reviewed in the weekly status. Typical FDE risks are data access, data quality, security approval, user adoption, scope creep and key-person availability on the customer side. Writing a risk down and sharing it is itself a mitigation: it turns a future surprise into a known, owned issue.
Change will come: a new stakeholder, a new use case, a discovery that the data is worse than expected. Handle it explicitly. Write the proposed change, its effect on timeline, criteria and effort, and get the sponsor's decision: swap it for something else in scope, extend, or defer it to the next phase. Saying "yes, and here is what moves" is how you stay helpful without losing the pilot.
Silent scope creep is the most common way good pilots fail: each small addition is reasonable, together they make the deadline impossible, and the decision meeting arrives with nothing finished.
The statement of work
Commercial engagements wrap the plan in a statement of work (SOW) agreed between the companies. As an FDE you usually help draft its technical parts. Make sure it contains the objective, scope and out-of-scope lists, deliverables, success criteria, customer responsibilities, timeline and milestones, acceptance process, assumptions, and how changes are handled. Anything vague in the SOW becomes a disagreement later; anything technical that is promised must be something you know you can deliver.